Deal anatomy · Badagry, Lagos

Emirate Dome, Badagry

A 24-metre-apex landmark dome. Complex geometry, structural steel and architectural finish.

Emirate Dome, Badagry

The problem

A landmark civic dome for a growing coastal city — with no precedent for delivery.

Badagry needed a signature civic structure that could serve as a marker for its growth: an assembly space at meaningful scale, structurally ambitious, delivered in a coastal environment with corrosion and cyclonic wind loading. There was no local precedent for a 24-metre-apex dome of this specification. The client wanted a build that would still be the town’s reference structure in fifty years.

The structure

Fixed-price, fixed-programme, self-delivered under one main contract.

Treaty took the project on a fixed-price, fixed-programme basis with structural steel, MEP and architectural finish self-delivered under one main contract. Foundations were designed to accommodate the coastal geotechnical profile. Steel was fabricated in Lagos, transported in sections and erected on site with a bespoke lifting sequence. Value engineering during design shaved 11% off the initial cost estimate without compromising the final architectural intent.

Contract
Fixed-price, fixed-programme, single main contract
Delivery model
Owner-operator self-delivery
Duration
22 months from mobilisation to handover
Sponsor
Cedar Group family

The delivery challenge

Steel geometry, coastal environment, tight civil calendar.

The two hardest problems were the geometric tolerance on the dome shell and the coastal environment. The dome required 216 unique steel members with tolerance below ±3mm across a 24-metre span; every member was digitally fabricated and pre-checked before shipment. Salt-air corrosion was controlled through a zinc-rich primer system with a specified 30-year service life, applied under humidity-controlled conditions. Civil works had to complete ahead of the rainy season to avoid a six-week weather delay.

  • Steel geometric tolerance
  • Coastal corrosion loading
  • Rainy-season civil deadline
  • Community access during works

The outcome

Delivered on programme, on budget, without a lost-time incident.

The dome opened on programme, within budget, and with zero lost-time safety incidents across the 22-month works. It has become the town’s reference civic structure and the anchor of a wider urban renewal masterplan. Post-handover monitoring continues under a whole-life asset-management brief with Treaty’s owner-operator team.

22 mo

On-programme delivery

No time extension

0

Lost-time incidents

Across 480,000 man-hours

±3mm

Steel tolerance

216 unique members

11%

Value-engineered saving

Off initial cost estimate

SDG alignment

  • Decent Work & Economic Growth
  • Industry, Innovation & Infra
  • Sustainable Cities & Communities
  • Partnerships for the Goals

Local content dashboard

  • Local labour96%

    Nigerian labour, of which 62% Badagry-local

  • Local materials71%

    Steel fabricated in Lagos; concrete, aggregates, block-work local

  • Local engineering100%

    Design and site engineering by Nigerian professionals

  • 340

    Jobs created during construction

Bring us the mandate

Similar problem? Similar structure?

Treaty applies the same approach to hospitals, marine works and civils across Africa.